Construction Lien Act · 1980 PA 497 · MCL 570.1101 et seq.

Michigan Construction Lien Rights: Deadlines, Notices, and How to Protect Payment

On a Michigan project, the right to pursue payment through a construction lien comes with a sequence of deadlines — and the sequence starts with paperwork, not with nonpayment. Here's the full timeline in plain English, with the statute's own deadlines: the 20-day Notice of Furnishing, the 90-day claim of lien, and the 1-year foreclosure window.

Plain English

What Lien Rights Are

The Construction Lien Act, and what it lets a contractor, subcontractor, laborer, or supplier do.

Michigan's Construction Lien Act — 1980 PA 497, MCL 570.1101 et seq. — gives people and companies that furnish labor or material to real property a legal path to pursue payment through the improved property itself: a construction lien. For a subcontractor or supplier who doesn't contract directly with the property owner, that path runs through a specific sequence of notices and deadlines, set out below.

Two honest framing points before the timeline. First, serving the notices and hitting the deadlines may support a potential lien claim — legal effect depends on the facts and applicable law. Second, this page is informational, not legal advice: for anything contested or uncertain, talk to a licensed Michigan construction attorney.

The Four Deadlines

The Michigan Lien Timeline

Each step keys off the one before it — and each has its own deadline in the act.

  1. Serve your Notice of Furnishing — within 20 days

    MCL 570.1109(1) (Sec. 109)

    After you first furnish labor or material, the act calls for serving a Notice of Furnishing within 20 days — on the designee and the general contractor, as named in the Notice of Commencement, at the address shown in it. Service is by personal delivery or certified mail; if it goes by certified mail, service is complete on mailing. Your first day on site or your first delivery starts the clock — not the contract date.

  2. Record your claim of lien — within 90 days after last furnishing

    MCL 570.1111(1) (Sec. 111) · MCL 570.1111(4)

    The right to a construction lien ceases to exist unless a claim of lien is recorded within 90 days after the lien claimant's last furnishing of labor or material. And for subcontractors, suppliers, and laborers, the claim must have a proof of service of the Notice of Furnishing attached — which is why step 1's paperwork matters months later.

    …the right of a contractor, subcontractor, laborer, or supplier to a construction lien created by this act shall cease to exist unless, within 90 days after the lien claimant's last furnishing of labor or material for the improvement, pursuant to the lien claimant's contract, a claim of lien is recorded in the office of the register of deeds…
    — MCL 570.1111(1) (Sec. 111), Michigan Construction Lien Act
    "A claim of lien by a subcontractor, supplier, or laborer shall have attached to it a proof of service of a notice of furnishing described in section 109."
    — MCL 570.1111(4), Michigan Construction Lien Act
  3. Serve a copy of the recorded claim on the designee — within 15 days

    MCL 570.1111(5) (Sec. 111)

    Recording isn't the last step. Within 15 days after the date of recording, a copy of the claim of lien — and of any recorded proof of NOF service — must be served on the designee, personally or by certified mail, return receipt requested. This is the only return-receipt-required service in the act. If this service is made by certified mail, service is complete upon mailing.

    …within 15 days after the date of the recording, shall serve on the designee personally or by certified mail, return receipt requested, at the address shown on the notice of commencement, a copy of the claim of lien and a copy of any proof of service recorded in connection with the claim of lien…
    — MCL 570.1111(5) (Sec. 111), Michigan Construction Lien Act
  4. File the foreclosure lawsuit — within 1 year of recording

    MCL 570.1117(1) (Sec. 117)

    A recorded lien only matters if it can be enforced. Proceedings to enforce a construction lien can't be brought later than 1 year after the date the claim of lien was recorded — miss that and the lien's enforcement window has passed. Section 117's text contains no extension mechanism; if a deadline is close, talk to a licensed Michigan construction attorney right away.

    Proceedings for the enforcement of a construction lien and the foreclosure of any interests subject to the construction lien shall not be brought later than 1 year after the date the claim of lien was recorded.
    — MCL 570.1117(1) (Sec. 117), Michigan Construction Lien Act

Deadlines in the act run on calendar language — "days after" furnishing or recording dates. Compute your 20-day NOF deadline free with the deadline calculator, or follow the whole preparation sequence in the NOF checklist.

Running Behind?

What Happens If the NOF Is Late

The notice you already missed doesn't have to be the notice you don't send.

A late NOF is better than no NOF. Under MCL 570.1109(5) and (6), Michigan law addresses how a late notice can affect the lien remedies available for work furnished before the notice is served — including limits when the owner has already paid the general contractor under a sworn statement or lien waiver. Work furnished after the notice is served is not the problem — the question is what remedies survive for the work that preceded it.

If you're late, send as soon as you can — and talk to a licensed Michigan construction attorney about your situation. Notice Track doesn't give legal advice.

Quick Answers

Michigan Lien Rights FAQ

What are construction lien rights in Michigan?

Michigan's Construction Lien Act (1980 PA 497, MCL 570.1101 et seq.) gives contractors, subcontractors, laborers, and suppliers a way to pursue payment for their work on real property through a construction lien. For subcontractors and suppliers who don't contract directly with the owner, the sequence starts with the Notice of Furnishing: serving it within the stated period may support a potential lien claim — legal effect depends on the facts and applicable law.

What is the deadline to send a Notice of Furnishing?

Under MCL 570.1109(1), a subcontractor or supplier provides the notice within 20 days after furnishing the first labor or material — served on the designee and the general contractor as named in the Notice of Commencement. Service can be personal or by certified mail, and certified-mail service is complete on mailing.

How long do I have to record a claim of lien?

Under MCL 570.1111(1), the lien right ceases to exist unless a claim of lien is recorded within 90 days after the lien claimant's last furnishing of labor or material. A claim of lien by a subcontractor, supplier, or laborer must also have a proof of service of the Notice of Furnishing attached to it (MCL 570.1111(4)).

How long do I have to foreclose on a Michigan construction lien?

Under MCL 570.1117(1), enforcement proceedings can't be brought later than 1 year after the date the claim of lien was recorded. Section 117's text contains no extension mechanism. If your window is closing, talk to a licensed Michigan construction attorney promptly — Notice Track doesn't give legal advice.

What happens if I send the NOF late?

A late NOF is better than no NOF. Under MCL 570.1109(5) and (6), Michigan law addresses how a late notice can affect the lien remedies available for work furnished before the notice is served — including limits when the owner has already paid the general contractor under a sworn statement or lien waiver. If you're late, send as soon as you can and talk to a licensed Michigan construction attorney about your situation.

Does serving an NOF guarantee I get paid?

No. Serving the notice within the stated period is one of the statutory steps that may support a potential lien claim — legal effect depends on the facts and applicable law, and no notice guarantees payment. Notice Track doesn't give legal advice; for anything contested, talk to a licensed Michigan construction attorney.

Notice Track is a technology platform and does not provide legal advice. Documents, deadline calculations, and information on this site are for informational purposes only and do not create an attorney-client relationship. For advice specific to your situation, consult a licensed Michigan construction attorney. Read our full disclaimers.

Start the Sequence on Time

Upload the document you already have — we build the NOF and mail it certified for $25, first one $20.

Get the free template by email

A blank Michigan NOF template, ready to print — plus how the 20-day deadline works. the full lien timeline

One email with the template. Occasional NOF deadline tips. Unsubscribe anytime. No spam, no sharing.

Review before mailing. Pay when we mail. No subscription required.

Notices go out by USPS Certified Mail with tracking.