Michigan Construction Lien Act: A Plain English Guide
Michigan's Construction Lien Act (Act 497 of 1980, MCL 570.1101 et seq.) governs when contractors, subcontractors, and material suppliers may pursue a construction lien after payment disputes. It is an important part of Michigan construction law, but it can be dense and difficult to navigate.
This guide breaks down the Act into plain English: who it covers, which deadlines matter, and how NOF requirements relate to a potential lien claim.
Who Does the Act Cover?
The Michigan Construction Lien Act applies to many parties who provide labor or materials to improve real property. This includes:
- General Contractors — prime contractors with direct contracts with the property owner
- Subcontractors — contractors hired by the GC (electricians, plumbers, HVAC, framers, etc.)
- Material Suppliers — businesses that supply lumber, plumbing supplies, electrical materials, and other building materials
- Laborers — individual workers who perform physical labor on a project
Design professionals (architects, engineers, surveyors) who provide services under a written contract may also be covered, subject to the applicable requirements, including any Notice of Furnishing rules under MCL 570.1109.
The Two Key Documents
The Act establishes two critical documents that subcontractors and suppliers should understand when evaluating a potential lien claim:
1. Notice of Furnishing (NOF) — MCL 570.1109
The NOF is a preliminary notice that tells the property owner and GC that you're working on the project. It must be served within 20 days of first providing labor or materials. Without it, subcontractors and suppliers may not be able to file a valid lien.
2. Construction Lien (Mechanics Lien) — MCL 570.1111
If payment is not received after serving an NOF, you may be able to file a construction lien (also called a mechanics lien), subject to the applicable facts and requirements. A lien must generally be recorded with the county Register of Deeds within 90 days after the last date you furnished labor or materials. If payment has stalled on an active project, see Michigan Subcontractor Not Paid? Here's What to Do — the action-first sequence from the NOF window through the lien deadlines.
⚠️ Key deadline distinction: The 20-day NOF deadline is measured from your FIRST day of work. The 90-day lien deadline is measured from your LAST day of work. Understanding which clock applies at each stage is critical.
How to Perfect a Lien Claim (4 Steps)
- Serve the Notice of Furnishing. Within 20 days of first furnishing labor or materials, prepare and send an NOF using the applicable requirements via Certified Mail to the Designee (or owner) and GC.
- Complete the work (or stop). Track your last date of furnishing — this starts the 90-day lien clock.
- Record the lien. Within 90 days of your last furnishing, file a sworn statement and claim of lien with the county Register of Deeds where the property is located. Include the legal description, amount claimed, and parties involved.
- Enforce the lien. After recording, you have one year to file a lawsuit to foreclose on the lien (MCL 570.1117). If you don't, the lien expires.
What Happens If You Miss These Deadlines?
- Miss the 20-day NOF? A late NOF may affect lien rights for work before and after service — and pre-notice work may be limited to the extent the owner already paid the GC under a sworn statement or waiver (MCL 570.1109(5), (6)).
- Miss the 90-day lien filing? You may lose the ability to pursue that lien remedy and may instead be an unsecured creditor against whoever hired you.
- Miss the 1-year enforcement? The lien expires by operation of law.
Note: A lien claim under the Michigan Construction Lien Act is a legal process. While Notice Track helps with the NOF step, recording and enforcing a lien involves court proceedings. We strongly recommend consulting a Michigan construction attorney for steps 3 and 4.
Common Misconceptions
- "I don't need an NOF if I have a contract." A contract with the GC does not necessarily substitute for serving an NOF on the property owner. Review the applicable statutory notice requirements for a potential lien claim.
- "The owner knows I'm working here, so I'm covered." Knowledge is not compliance. Actual service of the NOF via Certified Mail is required by law.
- "I can file a lien for the full contract amount even if I miss the NOF." A late NOF may affect lien rights for work before and after service — including limits when the owner already paid the GC under a sworn statement or waiver (MCL 570.1109(5), (6)). Whether a lien is available or what amount may be recoverable depends on the facts.
Related Michigan NOF Guides
Prepare your next NOF
Notice Track helps you prepare, send, and track your Michigan Notice of Furnishing, including Certified Mail delivery.
Get Started FreeNotice Track is a technology platform and does not provide legal advice. Documents, deadline calculations, and information on this site are for informational purposes only and do not create an attorney-client relationship. For advice specific to your situation, consult a licensed Michigan construction attorney. Read our full disclaimers.