Understanding Michigan's 20-Day Notice of Furnishing
The Notice of Furnishing (NOF) is the most critical document for any subcontractor or supplier working on a construction project in Michigan. If you don't send it on time, the availability or scope of a later construction lien claim may be affected if payment is not received.
What is a Notice of Furnishing?
A Notice of Furnishing is a written notice that informs the property owner and the general contractor that you are providing labor or materials to the project. It's not a lien; it's a preliminary notice related to a future lien claim.
The 20-Day Rule
In Michigan, you generally have 20 days from the date you first provided labor or materials to the project to deliver the Notice of Furnishing.
- For laborers, the deadline is 30 days from when wages were due.
- For subcontractors and suppliers, it's 20 days from the first day of work/delivery.
How to Deliver It
The act allows service of a notice of furnishing either personally or by certified mail (MCL 570.1109(1)); when it is served by certified mail, service is complete on mailing. Keep the certified-mail receipt and tracking record with your project records as proof of the mailing date. A return receipt is not required by the statute for a notice of furnishing.
Related Michigan NOF Guides
Prepare your next NOF
Notice Track helps you prepare, send, and track your Michigan Notice of Furnishing, including Certified Mail delivery.
Get Started FreeNotice Track is a technology platform and does not provide legal advice. Documents, deadline calculations, and information on this site are for informational purposes only and do not create an attorney-client relationship. For advice specific to your situation, consult a licensed Michigan construction attorney. Read our full disclaimers.