If you furnish labor or materials to a Michigan construction project and you don't contract directly with the owner, Michigan's Construction Lien Act (MCL 570.1109) generally calls for serving a Notice of Furnishing within 20 days of your first furnishing. The notice tells the property owner and general contractor you're furnishing to their project, and serving it within the stated period may support a potential lien claim — legal effect depends on the facts and applicable law. Service is by certified mail and is complete on mailing. Here's the process, step by step.
A blank Michigan NOF template, ready to print — plus how the 20-day deadline works.
Eight Steps
Work top to bottom — each step feeds the next one.
Ask the general contractor for a copy, or pull it from the register of deeds in the county where the property is located. Most of what your notice needs is on this recorded document.
Both are on the Notice of Commencement. Copy the legal description exactly as it appears — don't retype it from memory or shorten it.
All three are listed on the Notice of Commencement. These are the parties your notice names and is served on.
That's the day your crew first showed up or your materials were first delivered — not the contract date. Write it down; everything after this step keys off it.
The notice is due within 20 days of your first furnishing date. Count the days — or skip the arithmetic and let the calculator do the date math for you. Check your deadline free — no sign-up.
The notice is a statutory form. Enter the project details from the steps above plus your company information, and double-check every field against the source documents.
MCL 570.1109(1) calls for serving the notice by certified mail, and service is complete on mailing — your job is done when it's in the mail, addressed correctly.
The receipt is your record of when the notice was mailed; the tracking history shows its delivery progress. Keep both with your project records.
Process Pitfalls
Four things that trip up otherwise straightforward notices.
The legal description comes from the recorded Notice of Commencement. Copy it in full — a paraphrase from memory isn't the same thing.
The 20 days run from first furnishing — not from signing, invoicing, or the end of the month. If you're not sure of the date, compute it.
The clock starts at first furnishing, so paperwork saved for the end of a job can land outside the 20-day window. If you're already past it, see the FAQ below.
The receipt shows when you mailed the notice and the tracking shows delivery — without them you can't show either. File both with the project paperwork.
Quick Answers
Under Michigan's Construction Lien Act (MCL 570.1109), subcontractors and material suppliers who don't contract directly with the property owner generally serve one as part of the statutory requirements for a potential lien claim — suppliers serve the same notice.
A late NOF is better than no NOF. Under MCL 570.1109(5) and (6), Michigan law addresses how a late notice can affect the lien remedies available for work furnished before the notice is served. If you're late, send as soon as you can — and talk to a licensed Michigan construction attorney about your situation. Notice Track doesn't give legal advice.
This checklist and the deadline calculator are free — no sign-up. If you'd rather not fill out the form yourself, Notice Track prepares the NOF from the documents you upload, you review and approve it, and it's mailed by USPS Certified Mail with tracking: $25 per mailed notice, postage included, and your first one is $20.
Notice Track is a technology platform and does not provide legal advice. Documents, deadline calculations, and information on this site are for informational purposes only and do not create an attorney-client relationship. For advice specific to your situation, consult a licensed Michigan construction attorney. Read our full disclaimers.
Upload the document you already have — we build the NOF and mail it certified for $25, first one $20.
Review before mailing. Pay when we mail. No subscription required.
Notices go out by USPS Certified Mail with tracking.