How Subcontractors Can Meet Michigan NOF Requirements
If you're a subcontractor or material supplier in Michigan, lien rights can be an important legal remedy when payment disputes arise. Missing a paperwork deadline can affect whether and to what extent that remedy is available, even when the work was performed.
The #1 Reason Lien Rights Are Lost
The most common cause is missing the 20-day Notice of Furnishing deadline. Subcontractors forget, use regular mail instead of Certified Mail, or send to the wrong address. Any of these mistakes can affect the availability or scope of a lien claim.
5 Steps to Manage Michigan NOF Requirements
- Send an NOF on every project. Don't pick and choose based on risk — do it every time.
- Set a 15-day reminder. The 20-day deadline arrives fast. Give yourself a buffer.
- Verify the Notice of Commencement. Get the correct Designee, GC, and property info.
- Use Certified Mail. Regular mail doesn't count. Keep your receipt for proof.
- Track deadlines automatically. Notice Track helps you organize and monitor these steps.
Related Michigan NOF Guides
Prepare your next NOF
Notice Track helps you prepare, send, and track your Michigan Notice of Furnishing, including Certified Mail delivery.
Get Started FreeNotice Track is a technology platform and does not provide legal advice. Documents, deadline calculations, and information on this site are for informational purposes only and do not create an attorney-client relationship. For advice specific to your situation, consult a licensed Michigan construction attorney. Read our full disclaimers.